V1 Dual Binder Project

Waxahachie, Texas
IES Commercial & Industrial provided electrical and instrumentation services to upgrade our clients existing Binder & Washwater systems.
These systems play an important role in the manufacturing of fiberglass insulation and due to changes implemented by the Environmental Protection Agency required our client to upgrade these systems. Because of the importance of these systems there were two phases associated with this project, pre-outage and outage.

The pre-outage phase took place over a seven week duration while the plant was in operation. During this time IES installed control panels, conduit, pull 600V power cables and 300V or less instrumentation cables leaving the final connections to existing control panels, motor control centers and field devices to done during the plant outage.

Market Segment

Manufacturing

Engineering Type

Plan Spec